This Major Qualifying Project was completed in conjunction with Stantec to design upgrade options to increase septage treatment capacity at the Pease Wastewater Treatment Plant in Electrical and Computer Engineering, NH. Designs modernized existing technologies and suggested methods to treat glycol waste. Following a site visit, data analysis, design alternative development, and cost estimates, designs were scored in health and safety, environmental and sustainability, economic, and constructability criteria. This project proposes one short-term and one long-term design to resolve existing and future problems.

  • This report represents the work of one or more WPI undergraduate students submitted to the faculty as evidence of completion of a degree requirement. WPI routinely publishes these reports on its website without editorial or peer review.
Creator
Publisher
Identifier
  • E-project-032316-113340
Advisor
Year
  • 2016
Center
Sponsor
Date created
  • 2016-03-23
luogo
  • Portsmouth
Resource type
Major
Rights statement

Relazioni